Skip to content

Challenge

The site is next to a creek, with both water and rock to deal with. The new station went in beside the old concrete station it was replacing. Installation time had to be as short as possible, and ground disturbance had to be minimal.

What we supplied

An RPEQ certified 3.75m dia x 9.03m deep wet well and a separate 1.8m x 2.2m x 1.75m valve pit.

Why fibreglass

Townsville City Council and NQ Excavations knew from past experience that a Mullaly FRP pump station and valve pit could be installed in a short time with little ground disturbance.

"I would have no hesitation in recommending a Mullaly Fibreglass pump station as we have been installing these for over 15 years and have found the ease of installation, combined with the reduced safety risks and excavation works required make these units an overall cost effective solution and great value for our clients."

Eric Lollo, NQ Excavations